CONSTRUCTION NEWS & UPDATES FINAL EDITION       The finished surface paving has been completed.   The shoulder widening and the resurfacing of the curve have been completed.       TRAFFIC PATTERN CHANGES:   Traffic is now configured in its final position       We appreciate your attention to the 35 MPH [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on March 1st, 2012

CONSTRUCTION NEWS & UPDATES February 29 to March 17, 2012   The finished surface paving of the East bound lane has been completed.   The shoulder widening and the resurfacing of the curve have been completed.   The finished surface paving of the Bella Terra entrance is complete.   TRAFFIC PATTERN CHANGES:   Beginning Sunday [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on February 17th, 2012

CONSTRUCTION NEWS & UPDATES February 20 to March 10, 2012   Over the next three weeks paving will continue for both the East bound and West bound lanes and the entrances to all communities. The Bella Terra & Wildcat Run entrances are scheduled to be paved the night of February 20.   The shoulder widening [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on January 30th, 2012

CONSTRUCTION NEWS & UPDATES January 30 to February 20, 2012   Over the next three weeks construction will continue on the new East bound lane, to the South of existing Corkscrew Road and to the Eastbound entrance & thru lanes @ Bella Terra.   The shoulder widening was delayed again due to coordination issues with [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on January 3rd, 2012

CONSTRUCTION NEWS & UPDATES January 2 to January 21, 2011   Over the next three weeks construction will continue on the remaining new East bound lane, to the South of existing Corkscrew Road and to the Eastbound entrance & thru lanes @ Bella Terra.   The shoulder widening was delayed due to some design issues [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on December 7th, 2011

CONSTRUCTION NEWS & UPDATES December 12 to December 31, 2011   Over the next three weeks construction will continue on the remaining new East bound lane, to the South of existing Corkscrew Road and to the Eastbound entrance & thru lanes @ Bella Terra.   The shoulder widening is scheduled to resume during this period [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on November 21st, 2011

CONSTRUCTION NEWS & UPDATES November 21 to December 11, 2011   Over the next three weeks construction will continue on the new West bound lane, to the North of existing Corkscrew Road. The roadway will be paved in anticipation of relocating all traffic to the North the week of December 5. Lanes are narrow and [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on November 8th, 2011

CONSTRUCTION NEWS & UPDATES October 31 to November 18, 2011     Over the next three weeks construction will continue on the new West bound lane, to the North of existing Corkscrew Road. All traffic, from Ben Hill Griffin to the water treatment plant has been relocated to the South side of existing Corkscrew Road.  [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on October 6th, 2011

CONSTRUCTION NEWS & UPDATES October 8 to October 29, 2011     Over the next three weeks construction will continue on the new West bound lane, to the North of existing Corkscrew Road. All traffic, from Ben Hill Griffin to the water treatment plant has been relocated to the South side of existing Corkscrew Road.  [...]

Continue reading about CONSTRUCTION NEWS & UPDATES

Admin on September 20th, 2011

CONSTRUCTION NEWS & UPDATES September 17 – October 7, 2011     Over the next three weeks construction will intensify on the new West bound lane, to the North of existing Corkscrew Road. All traffic, from Ben Hill Griffin to the water treatment plant has bee relocated to the South side of existing Corkscrew Road.  [...]

Continue reading about CONSTRUCTION NEWS & UPDATES